As-Planned Schedule
The plan or baseline schedule the contractor developed to estimate/bid/contract to perform the work. The as-planned schedule incorporates planned production rates, work calendars, resource availability, logic ties, constraints and activity durations to meet contract requirements and contractor needs or desires.
Source: AACE International Recommended Practice No. 10S-90 - Cost Engineering Terminology